Hoc Mon and Cu Chi districts on May 6 spent about VND286 billion on site clearance compensation for 135 affected households of the Ring Road 3 project.
Although Ho Chi Minh City attempted to build more schools and classrooms as per the city People's Committee’s planning scheme for the school network, there exist large classes.
The standing committee of the HCMC Party Committee had a working session on innovation and completion of institutions and policies, and enhancement of effectiveness and efficiency of land management and use with the Ministry of Natural Resources and Environment on October 18.
The Ho Chi Minh City Transportation Works Construction Investment Project Management Authority, on the afternoon of October 16, coordinated with the Department of Transport of HCMC to hold a ceremony to open to traffic the Bung Bridge on Le Trong Tan Street that connects Binh Tan and Tan Phu districts.
Deputy Prime Minister Le Van Thanh on October 13 chaired a meeting on the progress of the eastern section of the North-South expressway project in the 2021-2025 period.
The People's Committee of Ho Chi Minh City has recently approved the design file of the marking of land boundaries for site clearance of component project 1 of the Ring Road No.3 project in HCMC to prepare for land boundary marking and hand over the site clearance boundary documents.
Amongst localities with the lowest disbursement of public investment capital, Ho Chi Minh City was asked to explain why the southern city has not achieved the plan at a nationwide conference on disbursement of public investment capital chaired by Prime Minister Pham Minh Chinh this morning.
The HCMC People’s Council coordinated with HCMC Television and the municipal Department of Information and Communications to organize the monthly ‘Citizens Ask – Government Answers’ session on works of compensation, site clearance and resettlement on September 11.
The Ho Chi Minh City Traffic Construction Investment Project Management Unit (Traffic Project Management Unit) coordinated with the Department of Transport of HCMC and the People's Committee of Nha Be District to hold a ceremony to hand over and receive the site to continue to develop the construction project of Long Kieng Bridge on the morning of September 8.
Mr. Nguyen Van Tham, Chairman of the People's Committee of Phu My Town, said that the town established four working groups to support the implementation of the Bien Hoa - Vung Tau Expressway project phase 1. The section through the town has a length of about 15.6km, and the estimated acquired land area is about 214ha of more than 1,100 households.
The Ministry of Transport (MoT) sent an official letter to the People’s Committee of Dong Nai Province on July 27 about speeding up the site clearance progress to soon start the construction and investment project of the first phase Tan Van-Nhon Trach section under the Ring Road No.3 in Ho Chi Minh City.
The Ministry of Transport (MoT) has approved 12 sub-projects of a mega project to build the eastern section of the North-South Expressway in the 2021-2025 period.
The Ministry of Transport has just approved the selection of contractor for the Nhon Trach bridge construction project and the path being the component project 1A under the construction investment project of the first phase Tan Van - Nhon Trach section of Ring Road No.3 in Ho Chi Minh City.
Speaking at the 14th meeting which was held by the Executive Committee of the Party Committee of HCMC’s District 3 of the 2020-2025 tenure on July 1, Chairwoman of the HCMC People’s Council Nguyen Thi Le asked the District 3’s authorities to speed up public investment disbursement and the site clearance progress for Metro Line No.2 project connecting Ben Thanh Market in District 1 and Tham Luong depot in District 12.
The 15th National Assembly (NA) adopted resolutions on some major road projects, including the construction project of Ring Belt No.3 of HCMC. In an interview with the Sai Gon Giai Phong Newspaper, Chairman of the HCMC People’s Committee Phan Van Mai shared information about the project's to-do list.
The Ministry of Transport yesterday said that the progress of the site hand-over serving for the Rach Mieu 2 Bridge construction project through the Mekong Delta provinces of Tien Giang and Ben Tre is slow.
After the National Assembly's approval, the Government will issue a resolution to conduct both site clearance and investment project formulation at the same time. Expressway projects in the Southern region can't be delayed further.