The 174.4-kilometer-long route including 86- kilometer long road surface and 88- kilometer overhead session will have a total investment of VND169,540 billion (over US$7 billion). As the project is put into exploitation, the passengers only take around 80 minutes to travel from Ho Chi Minh City to Can Tho City.
Accordingly, An Binh train station in An Binh Ward of Di An City, Binh Duong Province will be the starting point of cargo transport; and Tan Kien train station in Tan Kien Commune of Binh Chanh District, Ho Chi Minh City will be the starting point of passenger transport.
The ending point for both passenger and cargo trains shall be at Cai Rang station, Phu Thu Ward, Cai Rang District, Can Tho City.
The railway will travel through the provinces and cities of Binh Duong, Ho Chi Minh City, Long An, Tien Giang, Vinh Long and Can Tho.
Deputy Minister of Transport Nguyen Ngoc Dong concluded that the consultant contractors and localities need to study the planning focusing on the arrangement of station construction to determine the appropriate scale for the economy. Besides, the provinces and cities needed to submit the detailed planning to create a premise to exploit land funds and infrastructure, and to build a plan for the state and businesses to mutually participate in the construction of the station.