Từ khóa: #disbursement rate

Removing bottlenecks in public investment

Removing bottlenecks in public investment

Based on statistics, the public investment disbursement rate in HCMC was only 2 percent in the first quarter of 2023. If this situation persists, it may be challenging to achieve the disbursement plan of over VND70 trillion by the end of 2023.
Six ministries, four localities see zero percent disbursement rate

Six ministries, four localities see zero percent disbursement rate

By November 30, 54 localities and ten ministries had a disbursement rate below 50 percent. Of these, six ministries and four localities had zero percent disbursement rate. Three ministries and five localities saw a disbursement rate of over 50 percent of the capital plan.
Projects unable to disburse must urgently return capital to State budget

Projects unable to disburse must urgently return capital to State budget

Deputy Prime Minister Vu Duc Dam, Head of the Working Group No.3 on inspecting, urging, removing difficulties and obstacles, and accelerating disbursement of public investment capital in 2022, on October 26, worked with some ministries, agencies, and central and local agencies on the disbursement progress of public investment capital in 2022.
Six State-owned corporations fail to achieve revenue targets

Six State-owned corporations fail to achieve revenue targets

Six State-owned enterprises and corporations, including Vietnam Airlines Corporation, Airports Corporation of Vietnam, Vietnam Railways Corporation, Vietnam Coffee Corporation, and Vietnam Southern Food Corporation, failed to meet the annual revenue and profit targets. Vietnam Electricity could not achieve the revenue target despite having obtained the profit plan.
Disbursement of traffic projects reaches 40 percent of year plan: Ministry

Disbursement of traffic projects reaches 40 percent of year plan: Ministry

The Ministry of Transport on July 2 revealed that at the end of June 2021, its sub-divisions disbursed about VND43,401 billion, accounting for 40 percent of the plan for the entire year, higher than that during the same period last year and the average disbursement rate of the country.
A corner of Ho Chi Minh City (Photo: SGGP)

HCM City accelerates disbursement of public investment capital

Ho Chi Minh City had disbursed nearly VND21.28 trillion (US$920 million at current exchange rate) of public investment capital as of August 23, fulfilling 50.5 percent of the assigned capital this year, the city’s Department of Planning and Investment reported.
A view of the conference (Photo: SGGP)

HCMC party chief prompts public investment disbursement

HCMC has arranged funds for implementation of projects including those to solve traffic jam and the flooding but disbursement has been too slow, so agencies and districts citiwide should review public investment use for the last three years and propose several solutions on this issue.